高层剪力墙免支撑置换混凝土应用技术研究 被引量:1

RESEARCH ON APPLICATION TECHNOLOGY OF REPLACING CONCRETE WITHOUT SUPPORT FOR HIGH-RISE SHEAR WALL
下载PDF
导出
摘要 以济南某高层剪力墙结构施工至10层时发现2层混凝土远低于设计值,经对比确定采用免支撑置换混凝土方法进行加固。先通过结构计算结果确定墙体分段置换方案,再采用ABAQUS有限元软件模拟置换施工阶段及置换完成后的后续施工过程。随机取2层具有代表性的⑪/B-E轴间剪力墙为例进行监测,结果表明监测点应变大小与理论模拟值吻合良好,满足施工安全要求。 Taking a high-rise shear wall structure in Jinan as an example,the paper found that the concrete of the second floor was far lower than the design value after construction to the tenth floor of the structure.After comparison,the method of replacing concrete without support was determined for reinforcement.Firstly,the replacement scheme of the wall is determined by the structural calculation results,then the ABAQUS finite element software is used to simulate the replacement construction stage and the subsequent construction process after the replacement,and the representative 11/B-E-axis shear wall on the second floor is randomly selected as an example to monitor it,and the strain size of the monitoring point is in good agreement with the theoretical simulation value,meeting the safety requirements of the project construction.
作者 张建鹏 绳钦柱 牟强 崔珑 种道坦 何其斌 ZHANG Jian-peng;SHENG Qin-zhu;MU Qiang;CUI Long;CHONG Dao-tan;HE Qi-bin(Shandong Academy of Building Research Co.,Ltd.,250031,Ji'nan,China)
出处 《建筑技术》 2021年第2期219-222,共4页 Architecture Technology
关键词 剪力墙 免支撑 置换 有限元分析 应力 shear wall free support replacement finite element analysis stress
  • 相关文献

参考文献2

二级参考文献7

共引文献10

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部