摘要
文章基于北疆高寒地区百米级某拱坝坝体渗压计监测资料,分析坝体渗透压力异常现象的原因,分析认为施工期温度控制措施是关键因素,可为高寒地区建设同类型拱坝提供参考。
Based on the piezometer monitoring data of a hundred-meter arch dam in northern Xinjiang,the article analyzes the causes of the abnormal osmotic pressure of the dam.The analysis indicates that temperature control measures during the construction period are the key factor,and the article provides reference for the construction of similar arch dams in alpine region.
作者
韩世栋
李新
HAN Shidong;LI Xin(Nari Group (State Grid Electric Power Research Institute) Co., Ltd., Nanjing 211000,China;Xinjiang Administrative Bureau of Construction of Irtysh River Basin Development Project, Urumqi 830000,China)
出处
《西北水电》
2021年第1期60-64,共5页
Northwest Hydropower
关键词
高寒区
拱坝
首蓄期
渗透压力
alpine region
arch dam
initial storage period
osmotic pressure