摘要
根据山西某重组煤矿实际情况,提出了在新建矿井坑口总变电站变压器出口处增加限流电抗器的方案,以满足老旧设备短路分断容量,并通过了验证,有效解决了新建变电站系统短路电流过大对老旧井下设备所带来的一系列问题,同时降低未来新增设备技术要求,技术经济上具有较好的推广意义。
Based on the current situation of a restructured mine in Shanxi,this paper presents a plan to add current-limiting reactor at the exit of transformer in substation for the newly-built mining pits,in order to meet the criteria of short circuit breaking capacity of the old equipment,which has passed the test.It can solve a series of problems brought about by high short-circuit current in the newly-built substation system,and reduce the technical requirement of new equipment,which is well worth promoting in terms of technical economy.
作者
孙剑
SUN Jian(Taiyuan University of Science and Technology,Taiyuan 030024,China)
出处
《现代建筑电气》
2021年第2期51-54,共4页
Modern Architecture Electric
关键词
限流电抗器
短路电流
设备选型
线路阻抗
current limiting reactor
short circuit current
equipment selection
line impedance