期刊文献+

蒙华铁路万荣隧道粉细砂地层施工关键技术 被引量:3

Key Construction Technologies for Wanrong Tunnel of Menghua Railway Crossing Silty-Fine Sand Stratum
下载PDF
导出
摘要 针对蒙华铁路万荣隧道在穿越粉细砂地层施工过程中遇到的掌子面溜坍、超前水平旋喷桩间不咬合易漏砂、初期支护钢架直接立于松散砂层上导致沉降变形大等影响工程质量、威胁施工安全的主要问题,采用阶梯法开挖支护施工技术,周边旋喷桩帷幕超前支护;在格栅钢架拱脚增设钢垫板以扩大拱脚受力面积,增加钢架的稳定,减小因拱脚砂层松动引起较大的沉降变形;利用长仰拱栈桥施工仰拱,使仰拱结构封闭成环距掌子面距离不大于20 m,二次衬砌距掌子面距离不大于50 m;采用高压水喷雾器提高空气湿度,防止粉细砂层水分散失,降低其自然稳定性;并通过初期支护背后回填注浆补强等技术措施,有效防止溜坍,将沉降变形控制在5 cm以内。现场施工结果表明,上述施工技术措施有效地保证了万荣隧道穿越粉细砂地层的施工质量和施工安全。 During construction of Wanrong tunnel of Menghua railway crossing silty-fine sand stratum,many problems such as tunnel face collapse,sand leakage caused by untight advanced jet grouting piles,and large deformation caused by primary support steel frame in loose sandy stratum are encountered,which would affect the project quality and safety.Accordingly,relevant countermeasures are adopted as follows.(1)The stepped excavation support method and the advanced jet grouting pile curtain are adopted.(2)The steel shims are installed at grille steel frame feet to increase stress area,and further stabilize the steel frame and reduce the deformation induced by loose sandy stratum.(3)The long invert trestle is adopted to ensure that the distance between closed ring of invert structure and tunnel face be less than 20 m and that between secondary lining and tunnel face be less than 50 m.(4)The high-pressure water sprayer is used to improve the humidity in the air,avoid the moisture loss of silty-fine sand stratum,and reduce its natural stability.(5)The backfilling grouting behind the primary support is adopted to effectively reduce the collapse phenomenon and control the settlement deformation within 5 cm.The engineering practice results show that the above-mentioned technical measures can effectively ensure the construction quality and safety of Wanrong tunnel crossing silty-fine sand stratum.
作者 苏辉 SU Hui(Mengxi-Huazhong Railway Co.,Ltd.,Beijing 100073,China)
出处 《隧道建设(中英文)》 北大核心 2020年第S02期225-232,共8页 Tunnel Construction
关键词 铁路隧道 粉细砂层 旋喷桩帷幕 阶梯法 仰拱栈桥 钢垫板 含水率 railway tunnel silty-fine sand stratum jet grouting pile curtain step method invert trestle steel shim water content
  • 相关文献

参考文献13

二级参考文献102

共引文献175

同被引文献32

引证文献3

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部