期刊文献+

医院建筑工程变更控制研究 被引量:1

Study on change control of hospital construction project
下载PDF
导出
摘要 选择某医院建设项目进行了实例研究,通过对实例中每个变更数据统计分析,得出了各参建主体方变更的16种变更因素,并分析每个变更影响因素对造价影响的程度,识别出最敏感的变更因素,找出对敏感性因素更高效、经济可行的变更控制方法,对医院变更控制有事半功倍的效果。 In this paper,a hospital construction project was selected for a case study.Through the statistical analysis of each change data in the case,16 change factors of each participant were obtained,and the degree of impact of each change factor on the cost was analyzed.The most sensitive change factors were identified,and a more efficient and economically feasible change control method was found,which can get twice the result with half the effort for the hospital change control.
作者 庞灿 Pang Can(Shan County Central Hospital,Shanxian 274300,China)
机构地区 单县中心医院
出处 《山西建筑》 2021年第7期186-188,共3页 Shanxi Architecture
关键词 医院建筑工程 变更因素 敏感性 变更控制 hospital construction engineering change factor sensitivity change control
  • 相关文献

参考文献7

二级参考文献13

共引文献15

同被引文献3

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部