摘要
为研究地铁施工涉及复杂环境风险和管控措施,以南京地铁5号线建设为背景,对明挖区间下穿"高压走廊"进行风险分析和分级,找出高风险点,综合基坑工程、高压线杆等诸多影响因素,从设计、施工全方面制定安全技术措施,为类似工程施工风险管控提供参考。
In order to study the complex environmental risks and control measures involved in subway construction.Based on the construction of Nanjing Metro Line 5, the risk analysis and classification are carried out on the open excavation section crossing the "high voltage corridor", the high risk points are found out,from the design, construction of safety technical measures, to provide a reference for similar engineering construction risk control.
作者
周游
ZHOU You(Jiangsu Branch of Shanghai Tunnel Engineering Co.,Ltd,Nanjing Jiangsu 211100 China)
出处
《江苏建筑》
2021年第1期70-74,共5页
Jiangsu Construction
关键词
地铁明挖区间
高压走廊
风险
控制措施
open cut subway section
high voltage line corridor
risk
control measures