GIS调频式串联谐振耐压试验方案研究 被引量:1

Research on Voltage Withstand Test Scheme of Frequency Modulation Series Resonance for GIS
下载PDF
导出
摘要 为了检查220 kV六氟化硫组合电器安装后的绝缘性能,详尽阐述了对其进行交流耐压试验的步骤与操作方法,试验时特别要注意以下事项:试验前应对相关人员进行培训,促使其加强自我保护意识,对于未现场操作过高压耐压试验的调试人员,要在具有相关资质人员的指导下进行;耐压试验过程中要注意环境湿度与气体、粉尘对设备绝缘性能的影响,试验一般选在晴天进行;变频电源的输出值和额定容量能否达到耐压水平将影响整个试验的顺利进行;采取相应的辅助仪器来监测GIS耐压试验过程中是否放电以及放电部位,便于后期拆装检查与更换。 In order to check the insulation performance of 220KV sulfur hexafluoride combination electric appliance after installation,this paper describes the steps and operation methods of AC withstand voltage test in detail.Special attention should be paid to the following items during the test:before the test,relevant personnel should be trained to strengthen their self-protection awareness,and the commissioning personnel who have not operated the high voltage withstand voltage test on site should be under the guidance of relevant qualified personnel.Whether the output value and rated capacity of the variable frequency power supply can reach the withstand voltage level will affect the smooth progress of the whole test.The corresponding auxiliary instruments are used to monitor the discharge and the discharge position during the GIS withstand voltage test,which is convenient for later disassembly,inspection and replacement.
作者 冯相永 贾会星 李永泉 杨诚 FENG Xiangyong;JIA Huixing;LI Yongquan;YANG Cheng(College of Mechanical and Automotive Engineering,Chuzhou Vocational and Technical College,Chuzhou Anhui 239000,China;College of Continuing Education,Chuzhou Vocational and Technical College,Chuzhou Anhui 239000,China)
出处 《盐城工学院学报(自然科学版)》 CAS 2021年第1期22-25,共4页 Journal of Yancheng Institute of Technology:Natural Science Edition
基金 安徽省教育厅高校自然科学研究重点项目(kj2018a0836)。
关键词 GIS 串联谐振 耐压试验 试验方案 GIS series resonance withstand voltage test test scheme
  • 相关文献

参考文献3

二级参考文献31

  • 1周倩,唐炬,唐铭,谢颜斌,刘明军.GIS内4种典型缺陷的局部放电超高频数学模型构建[J].中国电机工程学报,2006,26(8):99-105. 被引量:52
  • 2GB50227-2008并联电容器装置设计规范[S].
  • 3[2]GB11032,交流无间隙金属氧化物避雷器[S].中国标准出版社,2000.
  • 4GB/T 311.1-1997,高压输变电设备的绝缘配合[S].
  • 5并联电容器组过电压和放电能量研究[R].能源部东北电力设计院.
  • 6CIGRE Working Group 33/32-12. Insulation co-ordination of GIS: return of experience, on site tests and diagnostic tech- niques [J]. Electra, 1998,176(2) :67-95.
  • 7Bolin P,Koch H. Introduction and applications of gas insulated substation(GIS) [C]// IEEE Power Engineering Society General Meeting. San Francisco, California, United States: IEEE Power Energy Society, 2005:920-926.
  • 8Kim J B,Kim M S,Park K S,et al. Development of monitoring and diagnostic system for SF6 gas insulated switchgear[C]// IEEE International Symposium on Electrical Insulation. Boston, Massachusetts, United States=IEEE Dielectrics and Electrical In- sulation Society, 2002 : 453-456.
  • 9IEEE Substations Committee Working Group K4. Partial dis- charge testing of gas insulated substations[J].IEEE Transac- tions on Power Delivery,1992,7(2) :499-506.
  • 10Baumgartner R, Fruth B, Lonz W, et al. Partial discharge, part X:PD in gas-insulated substations-measurement and practi cal considerations [J]. IEEE Electrical Insulation Magazine, 1992, 8(1): 16-27.

共引文献122

同被引文献4

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部