摘要 为了解决既有建筑内部改造过程中,因新增钢结构与老结构距离非常近而导致的施工空间有限,造成施工难度增大的问题,通过施工方案比选,最终选用整体提升施工工艺,成功解决了新增钢结构施工的难题。总结的经验.可为类似工程提供参考。 In order to solve the construction difficulty increased by the limited construction space due to close distance between the new steel structure and the old structure in the process of internal reconstruction of the existing building,and through the comparison and selection of construction schemes,the integral lifting construction technology is finally selected,and the construction difficulty of the new steel structure is successfully solved.The summarized experience can provide reference for similar projects.
作者 严凤英 YAN Fengying(Shanghai Mechanized Construction Group Co.,Ltd.,Shanghai 200072,China)
出处 《建筑施工》 2021年第3期436-438,共3页 Building Construction
关键词 既有建筑 新增钢结构 施工空间有限 整体提升 existing buildings new steel structure limited construction space integral lifting

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部