同步顶升更换支座的过程模拟及效果分析 被引量:3

Process Simulation and Effect Analysis of Support Replacement by Synchronous Lifting
下载PDF
导出
摘要 结合哈尔滨市二道河桥加固维修工程实例,分析其更换支座过程中主梁应力、主梁位移及T梁近端主应力值等的变化情况,并与成桥模型计算值进行比较,分析该桥更换支座过程中梁体的受力状态发生的变化,并结合该桥加固后的荷载试验,验证了其加固改造效果。 In combination with the reinforcement and maintenance project of the bridge over Erdaohe river in Harbin,the changes of main beam stress,main beam displacement and main stress value of near end of T-beam in the process of support replacement are analyzed,and compared with the calculated value of the model of the completed bridge.The changes of stress state of beam body in the process of bridge support replacement are analyzed.In combination with the load test after the reinforcement of the bridge,the reinforcement and reconstruction effect is verified.
作者 李锋丹 Li Fengdan(Shandong Province Highway Design Consulting Co.,Ltd.,Jinan 250000,China)
出处 《北方交通》 2021年第4期17-20,共4页 Northern Communications
关键词 T梁桥 同步顶升 更换支座 模拟分析 T-beam bridge Synchronous lifting Support replacement Simulation analysis
  • 引文网络
  • 相关文献

参考文献4

二级参考文献20

共引文献132

同被引文献12

引证文献3

二级引证文献9

;
使用帮助 返回顶部