超浅埋超小净距花岗岩隧道中两种开挖工法的受力分析

Stress Analysis of Two Excavation Methods in Ultra-Shallow Buried and Ultra-Small Clear Distance Granite Tunnel
下载PDF
导出
摘要 结合某隧道工程,提出“三台阶法+钢管桩”开挖工法,通过建立力学模型,模拟计算常规CD法开挖与“三台阶法+钢管桩”开挖的受力情况,并对2种工法经济效益进行分析。结果表明:应用“三台阶法+钢管桩”不仅缩短工期,而且经济效益更高。 Combined with a tunnel project,this paper puts forward"three steps method+steel pipe pile"excavation method,by establishing a mechanical model,the stress of conventional CD method and"three-step method+steel pipe pile"excavation is simulated and calculated.And the economic benefit of the two construction methods is analyzed.The results show that the application of"three-step method+steel pipe pile"not only shortens the construction period,but also has higher economic benefit.
作者 聂佳佳 NIE Jia-jia(CCCC First Highway Huanan Engineering Co.Ltd.,Guangzhou 511300,China)
出处 《工程建设与设计》 2021年第7期65-67,共3页 Construction & Design for Engineering
关键词 超浅埋超小净距隧道 CD法 三台阶法+钢管桩 受力分析 ultra-shallow buried and ultra-small clear distance tunnel CD method three step method+steel pipe pile stress analysis
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部