摘要
文章介绍了内蒙古大唐国际克什克腾煤制天然气有限责任公司二期变换装置变换炉。首先分析了问题的来源,根据GB 150.3—2011进行了专业的分析,针对变换炉在改扩建项目有机硫转化及烯烃饱和装置中利旧的可行性进行了计算与分析。
This paper introduces the second phase conversion device conversion furnace of Inner Mongolia Datang International Keshiketeng Coal Gas Co.,Ltd.Firstly,the source of the problem is analyzed,and the professional analysis is carried out according to GB 150.3—2011.The feasibility of utilizing the old shift converter in the organic sulfur conversion and olefin saturation unit of the reconstruction and expansion project is calculated and analyzed.
作者
赵巍
ZHAO Wei(Inner Mongolia Datang International Keshiketeng Coal Gas Co.,Ltd.,Chifeng 025350,China)
出处
《化工管理》
2021年第10期186-188,共3页
Chemical Engineering Management
关键词
煤化工
变换设备
利旧
coal chemical industry
transformation equipment
utilize old equipments