大跨度装配式框架结构中心岛波浪式施工流程建造技术 被引量:1

Construction Technology of Wave Construction Process for Center Island of Large Span Fabricated Frame Structure
下载PDF
导出
摘要 以上海地区某立体式公交停车场项目为例,结合双T板厂家生产运输能力,现场吊装专业水平,和缓凝结预应力张拉时限制订相应的施工方案。通过施工方案比较,吊装顺序及合理分块施工方案优化,波浪式施工吊装流程有效地节约了工期,为类似工程提供实践经验。 Taking a three-dimensional bus parking lot project in Shanghai as an example,combined with the production and transportation capacity of double-t-plate manufacturers,the professional level of on-site hoisting,and the limitation of the construction scheme during the tension of slow setting prestress is tensioned.Through the comparison of construction schemes,the hoisting sequence and reasonable block construction scheme optimization,the wave construction hoisting process effectively saves the construction period,and provides valuable practical experience for similar projects.
作者 邢嘉陆 Xing Jia-lu
出处 《建筑技术开发》 2021年第5期9-11,共3页 Building Technology Development
关键词 重荷载 大跨度 双T板 缓凝结预应力 波浪式施工 heavy load large span double t-slab slow setting prestress wave construction
  • 相关文献

同被引文献7

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部