摘要
东安湖体育公园三馆项目采用多种幕墙系统,其中小球馆采用抗风柱+吊杆横明竖隐玻璃幕墙系统,其运输及安装为本工程重难点。现场将抗风柱、横梁放在支托架上,用小平板车运输;在顶结构上固定电动葫芦与定滑轮组进行吊装;安装完成后进行幕墙质量检测,最终保证幕墙系统安全可靠。
Dongan Lake Sports Park Third Hall project using a variety of curtain wall system,among them,the small-ball arena adopts the wind resistance column+boom-type horizontally-exposed and vertically-hidden glass curtain wall system,its transportation and installation are the major and difficult points.The wind resistance column and beam is placed on the support bracket,transported by small flatcar.The electric hoist and fixed pulley group are fixed on the top structure for hoisting.After installation,curtain wall quality inspection is carried out to ensure the safety and reliability.
作者
王晋
龙叶天
尹凌川
王光武
程建刚
陈炜航
袁贵福
李铉诚
艾维
刘智
WANG Jin;LONG Yetian;YIN Lingchuan;WANG Guangwu;CHENG Jiangang;CHEN Weihang;YUAN Guifu;LI Xuancheng;AI Wei;LIU Zhi(Southwest Branch,China Construction Third Engineering Bureau Group Co.,Ltd.,Chengdu,Sichuan 610041,China;Chengdu China Resources Land Yidu Real Estate Co.,Ltd.,Chengdu,Sichuan 610100,China)
出处
《施工技术》
CAS
2021年第6期58-60,共3页
Construction Technology
关键词
体育馆
安装工程
幕墙
运输
稳定性
施工技术
stadiums
installation
curtain wall
transportation
stability
construction