城市轨道交通盾构法瓦斯隧道造价研究 被引量:3

Study on Cost of Shield Gas Tunnel in Urban Rail Transit
下载PDF
导出
摘要 目前,城市轨道交通领域缺乏瓦斯隧道的费用计算办法及相关的依据标准。成都市轨道交通18号线工程作为全国城市轨道交通中第一个穿越高、低瓦斯区域的项目,与之相关的造价测算是各方都关注的热点问题。本文以该工程为例,从盾构机防爆改装、隧道通风、瓦斯监测及检测、瓦斯隧道密封性、瓦斯隧道智能门禁系统、临时设施费等方面,对盾构法瓦斯隧道的造价进行分析与研究,提出了盾构法瓦斯隧道的合理计算方法及技术经济指标,为合理控制投资提供依据,为今后类似项目造价测算提供借鉴。 There is a lack of cost calculation methods and relevant standards for gas tunnels in current urban rail transit cost system.Chengdu rail transit Line 18 is the first urban rail transit to pass through high and low gas areas in China,and the related cost calculation is a hot issue concerned by all parties.Taking the project as an example,this paper analyzes and studies the cost of shield gas tunnel from the aspects of shield machine explosion-proof modification,tunnel ventilation,gas monitoring and detection,gas tunnel sealing,gas tunnel intelligent access control system,temporary facility cost,etc.The reasonable calculation method and thetechnical and economic index of shield gas tunnel are put forward to provide the basis for reasonable control of investment and provide reference for cost calculation in similar projects.
作者 陈雅麒 CHEN Ya-qi(China railway eryuan engineering group co.ltd Institute of Engineering Economics,Chengdu 610031,China)
出处 《铁路工程技术与经济》 2021年第2期50-53,共4页 Railway Engineering Technology and Economy
关键词 城市轨道交通 盾构法 瓦斯 甲烷 造价 概算 urban rail transit shield method gas methane cost budget estimate
  • 相关文献

参考文献1

二级参考文献5

共引文献3

同被引文献26

引证文献3

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部