摘要
利用数理统计分析和水文水利计算方法,计算沟坝河大桥桥址断面设计洪峰流量、设计洪水水位、壅水高度、冲刷深度等相关技术指标,结合桥址断面所在河段防洪任务,防洪标准和桥位河段防洪工程建设等实际情况,对建设项目的防洪影响进行综合评价,结果表明:拟建沟坝河大桥按照相关法律法规设计;建成后的大桥满足河道行洪安全和河道的防洪标准,对河道整体河势的稳定影响较小.
By means of mathematical statistics analysis and hydrology and water conservancy calculation methods,relevant technical indexes such as designed flood peak discharge,designed flood level,backwater height and scour depth of bridge site section are calculated.Combined with the flood control task,the flood control standard and the flood control engineering construction of the river bridge site,the flood control impact of the construction project is comprehensively evaluated.The results show that there is no contradiction between the proposed Gouba River Bridge and relevant laws and regulations.The completion of the bridge does not affect the river flood safety,does not reduce the flood control standards of the river,the overall stability of the river less impact.
作者
赵春霞
董玉云
丁庆洋
ZHAO Chun-xia;DONG Yu-yun;DING Qing-yang(School of Civil Engineering,LanzhouJiaotong University,Lanzhou 730070,China)
出处
《兰州工业学院学报》
2021年第2期39-42,59,共5页
Journal of Lanzhou Institute of Technology
基金
国家自然科学基金(50579064)
长江学者和创新团队发展计划(RIT1139)。
关键词
沟坝河大桥
水文计算
冲淤计算
影响评价
Gouba River Bridge
hydrologic calculation
calculation of scouring and silting
impact assessment