期刊文献+

三峡升船机日运行厢次分析 被引量:2

Daily operation times of the Three Gorges ship lift
下载PDF
导出
摘要 通过规范公式和运行实际分析升船机运行的时间指标构成,对三峡升船机运行过程中各个环节所需的时间指标及相关运行方式进行分类统计及验算。分别测算了不同速度条件下三峡升船机单向运行和双向运行条件下的日运行厢次,为未来优化升船机运行及相关技术规范修订提供技术支撑。 Based on the analysis of the time index of ship lift operation in the standard formula and the actual operation,the time index of each link in the Three Gorges ship lift operation was classified,counted and checked.The daily running times of the Three Gorges ship lift under the conditions of unidirectional operation and bidirectional operation under the different speed conditions were calculated respectively.The results can provide technical support for the future optimization of ship lift operation technical specifications.
作者 张义军 ZHANG Yi-jun(The Yangtze River Shipping Development Research Center,Wuhan 430014, China)
出处 《水道港口》 2021年第1期89-93,共5页 Journal of Waterway and Harbor
基金 国家自然科学基金(51809130) 三峡后续工作科技项目资助(SXHXGZ-SCJ-2020-3)。
关键词 升船机 厢次间隔时间 设备运行历时 船舶进出厢 日运行厢次数 ship lift interval time of lift equipment running time ship in and out of lift daily running times
  • 相关文献

参考文献5

二级参考文献43

  • 1金卓.三峡升船机解析[J].武汉交通职业学院学报,2008,10(2):79-82. 被引量:7
  • 2左东启.水工设计手册[M].北京:水利电力出版社,1987.389-423.
  • 3周华兴.船闸闸室断面系数与阻力、航速有关的初步探讨[J].水道港口,1983,(1):18-25.
  • 4田咏沅.三峡水利枢纽升船机研究[J].人世长江,1986,(5):5-13.
  • 5杨铁英.关于顶推船队进出12m宽船闸的实船和模型试验[J].水运工程,1979,(4):13-18.
  • 6包钢鉴 等.福建水口水电站工程2×500t级垂直升船机整体模型试验研究总报告[M].南京:南京水利科学研究院,1995..
  • 7宗幕伟.陆水升船机中间试验水力学模型试验报告[M].南京:南京水利科学研究院,1965..
  • 8董兴林 王念慎.升船机船厢设计中的水力学问题[M].北京:北京水利水电科学研究院,1986..
  • 9覃祥孝,李然.大型人字门同步升降系统的开发与应用[J].流体传动与控制,2007(5):48-50. 被引量:4
  • 10杨逢尧,于庆奎.三峡升船机金属结构与机械设备的关键技术问题[J].人民长江,1997,28(10):33-35. 被引量:2

共引文献24

同被引文献18

引证文献2

二级引证文献3