摘要
某金矿选矿厂采用一段磨矿+一段浮选工艺流程,磨矿系统改造为自动化控制系统后,存在一系列问题,通过工艺参数优化,实现产能优化提升。
A gold ore dressing plant adopts the process of one-stage grinding+one-stage flotation.After the grinding system is transformed into an automatic control system,there are a series of problems.Through the optimization of process parameters,the productivity is optimized and improved.
作者
刘颖
隆岗
温建波
LIU Ying;LONG Gang;WEN Jian-bo(Technical center of China mining gold Co.,Ltd,Yantai 264010,China)
出处
《世界有色金属》
2021年第4期40-41,共2页
World Nonferrous Metals
关键词
入磨粒度
溢流浓度
返砂比
grinding particle size
overflow concentration
sand return ratio