深水钻井导管水下打桩站立稳定性分析与建议

Deepwater Subsea Driving Drilling Conductor Standing Stability Analysis and Optimization
下载PDF
导出
摘要 分析了钻井导管水下打桩安装工艺在施工过程中所面临的导管站立稳定性问题。由于国内未进行深水钻井导管水下打桩实践,关于导管海底站立稳定性问题的分析及优化设计的指导性文献较少。基于现有标准及国外已有实践,分析了现有几种导管站立稳定性分析方法的特点与适用性,剖析了导管稳定性的工况、载荷及关键影响因素。提出了导管站立稳定性分析方法的应用建议。为深水钻井导管水下打桩技术在南海应用提供参考。 The issue of conductor standing stability during the implementation of deepwater subsea driving drilling conductor in the deepwater oil and gas development construction was analyzed.Since there is no underwater piling practice of deepwater drilling pipes in China,there are few specific guidance and paper about deepwater drilling conductor standing stability issues including analysis and optimization.Based on history practices and industrial standards,the features of feasibility of conductor standing stability related methods,the load cases considerations and key influent factors were analyzed.The stability optimization method and suggestion were proposed to provide references for subsea driving conductor application in South China Sea deepwater development.
作者 邓玉明 DENG Yuming(CNOOC Energy Technology & Services Limited,Shenzhen 518067,China)
出处 《石油矿场机械》 CAS 2021年第3期17-22,共6页 Oil Field Equipment
基金 中国海洋石油集团有限公司十三五重大科技项目“南海深水钻完井关键技术研究”课题1“深水钻完井关键技术研究”(CNOOC-KJ135ZDXM05LTD01 SHENHAI 2016)。
关键词 深水 导管 站立稳定性 分析 deep water conductor standing stability analysis
  • 相关文献

参考文献8

二级参考文献52

共引文献47

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部