临时墩不均匀竖向变形对顶推施工影响分析 被引量:2

Analysis of influence of uneven vertical deformation of temporary pier on incremental launching construction
下载PDF
导出
摘要 以112 m简支钢箱拱桥步履式多点顶推施工过程分析为背景,利用有限元软件Midas Civil建立了临时墩和顶推模型,结合现场监测数据,分析了支点刚度和临时墩不均匀沉降对钢箱拱顶推施工的影响。发现支点刚度相差过大和临时墩不均匀沉降会引起支点处梁体竖向强制位移,甚现出现“支点脱空”现象,导致主梁和导梁应力增大,并提出采用千斤顶反向预压提前消除临时墩非弹性变形,进一步分级抽垫钢板精调墩顶标高的解决方案。 Based on the analysis of multi-point incremental launching construction process of 112m simply supported steel box arch bridge,the model of temporary pier and incremental launching is established by using the finite element software MIDAS civil.Combined with the field monitoring data,the influence of fulcrum stiffness and uneven settlement of temporary pier on incremental launching construction of steel box arch bridge is analyzed.It is found that the large difference in the stiffness of the fulcrum and the uneven settlement of the temporary pier will cause the vertical forced displacement of the beam body at the fulcrum,and even the phenomenon of"fulcrum disengaging",which leads to the increase of the stress of the main beam and the guide beam.It is proposed that the non elastic deformation of the temporary pier can be eliminated in advance by using jack reverse preloading,and the elevation of the pier top can be adjusted accurately by using the stepped cushion steel plate.
作者 岳昊 孙泓发 赵云凯 王常峰 YUE Hao;SUN Hongfa;ZHAO Yunkai;WANG Changfeng(Yantai University,Yantai 264005,China)
机构地区 烟台大学
出处 《四川建材》 2021年第5期165-166,共2页 Sichuan Building Materials
关键词 顶推施工 临时墩 沉降 竖向刚度 反向预压 launching construction temporary pier subsidence vertical stiffness reverse preloading
  • 相关文献

参考文献3

二级参考文献67

共引文献168

同被引文献11

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部