屯兰矿18407工作面巷道支护设计及安装 被引量:2

Design and Installation of Roadway Support in 18407 Working Face of Tunlan Mine
下载PDF
导出
摘要 以屯兰矿18407工作面为例,分析了该工作面的地质和巷道布置概况,分别讨论了两顺槽、切眼和底抽巷的断面尺寸是否满足要求,并对巷道支护中的锚杆长度和间距、锚索长度和间距等重要参数的计算方法进行研究,提出了特殊条件下巷道的加强支护方案,对锚杆、锚索等支护材料的安装技术要求进行了分析,为进一步提高支护稳定性及安装效率提供了依据。 Taking 18407 working face of Tunlan coal mine as an example,this paper first analyzes the geology and roadway layout of the working face,and then discusses whether the cross-section size of two crossheading,cut and bottom extraction roadway meets the requirements,and studies the calculation method of important parameters such as bolt length and spacing,anchor cable length and spacing in roadway support,and then puts forward the design method of roadway under special conditions Finally,the technical requirements for the installation of bolt,anchor cable and other supporting materials are analyzed.
作者 张大辉 Zhang Dahui(Shanxi Coking Coal Group Xishan Coal and Power Tunlan Coal Mine,Taiyuan Shanxi 030052)
出处 《机械管理开发》 2021年第3期43-45,共3页 Mechanical Management and Development
关键词 巷道支护 参数计算 锚杆 锚索 安装 roadway support parameter calculation bolt anchor cable installation
  • 相关文献

参考文献6

二级参考文献28

共引文献39

同被引文献7

引证文献2

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部