城郊矿水文孔高压出水封堵方案研究

Study on Plugging Scheme of High Pressure Outlet Water from Hydrological Hole of Chengjiao Mine
下载PDF
导出
摘要 为解决城郊矿井下水文孔高压出水问题,提出了采用止水塞+注浆堵漏的工艺方案。止水塞外层采用弹性橡胶体结构,能有效适应不规则的水文孔结构,实现初步止水。在注浆过程中采用连续注浆和间歇式注浆相结合的方案实现了堵漏安全性和快速性的统一。该堵漏工艺方案能够有效解决水文孔高压出水问题。 In order to solve the problem of high-pressure water outflow from underground openings in Chengjiao Coal Mine,the technological scheme of sealing plug and grouting is put forward.The outer layer of water stop plug adopts elastic rubber structure,which can effectively adapt to irregular hydrologic hole structure and realize preliminary water stop.In the process of grouting,continuous grouting and intermittent grouting are combined to achieve the unity of safety and rapidity of plugging,which can effectively solve the problem of high-pressure water outflow from hydrological hole.
作者 王传永 Wang Chuanyong(Chengjiao Coal Mine of Yongmei Company of Henan Energy and Chemical Industry Group,Henan Yongcheng 476600)
出处 《山东煤炭科技》 2021年第5期175-177,共3页 Shandong Coal Science and Technology
关键词 水文孔 止水塞 注浆堵漏 hydrologic hole water stop plug grouting plugging
  • 相关文献

参考文献4

二级参考文献49

共引文献48

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部