摘要
介绍了某电厂原煤仓清堵装置控制回路运行中存在的缺陷和电气故障现象,分析了异常产生的原因,提出了原煤仓清堵装置控制回路改进的具体方案和完善措施。改进后效果良好、效益显著,为给煤系统稳定运行和机组安全稳定提供了保障。
This paper introduces the electrical defects and faults in the operation of the control circuit of the raw coal bunker blockage removing device in a power plant,analyzes the causes of the abnormalities,and puts forward a specific scheme and measures for control circuit improvement.The improvements have resulted in good effectiveness and significant benefits,which in turn provides guarantee for the safe and stable operation of coal feeding system of the boiler and the power unit.
作者
池慧勇
邬俊
白绪超
杨文池
CHI Huiyong;WU Jun;BAI Xuchao;YANG Wenchi(Inner Mongolia Jingneng Kangbashi Thermal Power Co.,Ltd.,Ordos 017000)
出处
《电力安全技术》
2021年第5期55-58,共4页
Electric Safety Technology
关键词
清堵装置
控制回路
电气缺陷
blockage removing device
control circuit
electrical defects