摘要 以济南地铁1号线王大区间为依托,在高压旋喷桩加固失效的情况下,采用液氮垂直冻结加固技术使冻结土体有效承载水土压力,阻挡地下水携砂流入接收井,保证洞门破除安全。通过方案比选,选用盾构水下接收技术,可平衡水土压力,有效控制地面沉降,保护地下管线。 This paper introduces the technology based on the Jinan Subway Line 1 Wangfuzhuang to Dayang station section.In the case of high pressure jet grouting pile reinforcement failure,the frozen soil can bear the soil and water pressure effectively adopt liquid nitrogen vertical freezing reinforcement technology.It can block the flow of groundwater carrying sand into the receiving well,and ensure the safety of the broken door.Through the scheme selection,shield underwater receiving technology is selected.It can balance water and soil pressure,and effectively control land subsidence,protect underground pipeline.
作者 张中勇 邱光明 路林海 武朝军 王彪 耿传政 ZHANG Zhongyong;QIU Guangming;LU Linhai;WU Chaojun;WANG Biao;GENG Chuanzheng(Jinan Rail Transit Group Co.,Ltd.,Jinan,Shandong 250101,China;China Railway Design Group Co.,Ltd.,Tianjin 300308,China;China Railway 14th Bureau Group Co.,Ltd.,Jinan,Shandong 250101,China)
出处 《施工技术》 CAS 2021年第9期110-112,共3页 Construction Technology
基金 山东省住房和城乡建设厅2016年专项基金。
关键词 地铁 盾构 冻结土 加固 施工技术 subways shields frozen soils reinforcement construction
  • 相关文献

参考文献11

二级参考文献71

共引文献95

同被引文献14

引证文献3

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部