剧场舞台设施设备综合安装方案创新实例

Innovative Example of Comprehensive Installation Scheme of Theater Stage Facilities and Equipments
下载PDF
导出
摘要 南通大剧院项目建设工期紧,且质量要求高。为在最短的工期内实现舞台设备的安装,巧妙利用了舞台机械设备可拆卸安装的特点,通过安装方案的工序调整与创新,利用台面钢结构层进行竖向空间划分,使工程可在同一垂直空间、不同水平空间内同时展开施工,既解决室内大体量舞台机械施工工期紧张的难题,同时也为打造精品工程创造了有利的条件。 The construction period of Nantong Grand Theater project is tight,and the quality requirements are high.In order to realize the installation of stage equipment in the shortest construction period,the characteristics of detachable installation of stage mechanical equipment are skillfully used.Through the process adjustment and innovation of installation scheme,the vertical space is divided by using the steel structure layer of table top,so that the project can be carried out in the same vertical space and different horizontal space at the same time,which not only solves the problem of tight construction period of indoor large-scale stage machinery,but also creates favorable conditions for building highquality projects at the same time.
作者 修亚光 胡双 陈文龙 管仁仁 XIU Yaguang;HU Shuang;CHEN Wenlong;GUAN Renren(China Construction Eighth Engineering Division Co.,Ltd.,Shanghai 200135,China)
出处 《建筑施工》 2021年第5期838-840,共3页 Building Construction
关键词 舞台机械 安装 同时作业 施工平台 stage machinery installation simultaneous operation construction platform
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部