塘厦西南联络线上跨营业线T梁施工控制技术 被引量:2

Control technology of T-beam construction cross business line in Tangxia southwest linking-up road
下载PDF
导出
摘要 跨营业线运架T梁施工影响因素多,施工难度大,是桥梁施工中的难点。本文结合塘厦西南联络线第9孔到第11孔上跨营业线运架T梁施工实践,详细阐述了跨营业线运架T梁施工方法、施工要点、架设时间节点与临边防护,为解决跨营业线运架T梁施工问题提供了技术参考。 With many influencing factors and difficulties in construction,T-beam construction cross the operating railway is a difficult problem in the bridge construction.Combined with the construction practice of T-beam transportation and erection crossing operating railways at No.9 to No.11 hole of Tangxia southwest linking-up road,the construction method,construction key points,erection time node,and edge protection of T-beam transportation and erection crossing operating railways were expounded in detail,which provided technical reference for solving the construction problems of T-beam transportation and erection crossing operating railways.
作者 王鑫鹤 WANG Xin-he(China Railway 19th Bureau Group No.5 Engineering Co.,Ltd.,Dalian 116100,Liaoning,China)
出处 《资源信息与工程》 2021年第3期106-108,111,共4页 Resource Information and Engineering
关键词 塘厦西南联络线 跨营业线 T梁施工 Tangxia southwest linking-up road cross operating railway T-beam construction
  • 相关文献

参考文献3

二级参考文献3

共引文献18

同被引文献14

引证文献2

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部