带转换层框架-剪力墙结构支模施工技术

Formwork Erection Construction Technology of Frame Shear Wall Structure with Transfer Floor
下载PDF
导出
摘要 以深圳大学行政办公与科研专职用房为例,提出了带转换层框架-剪力墙结构支模施工技术方案。技术方案解决了转换层中悬挑部分的支模体系架设问题,为项目的顺利实施提供了施工保障,可为类似结构支模提供借鉴。 Taking the administrative office and full-time scientific research staff room of Shenzhen University as an example,the formwork erection construction scheme of frame shear wall structure with transfer floor is proposed.The technical scheme solves the problem of erecting the formwork system of the cantilever part in the transfer floor,provides construction guarantee for the smooth implementation of the project and can provide reference for similar structure formwork.
作者 张利锋 ZHANG Lifeng(Shanghai Construction No.4(Group)Co.,Ltd.,Shanghai 201103,China)
出处 《建筑施工》 2021年第6期1039-1041,共3页 Building Construction
关键词 支模 转换层 剪力墙结构 施工技术 formwork erection transfer floor shear wall structure construction technique
  • 相关文献

参考文献4

二级参考文献12

共引文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部