摘要
同期点的选择一般与主接线形式和运行方式密切相关。垃圾焚烧发电厂属小机组电厂,一般机组出力为9~30 MW不等,针对这样小容量机组的电厂,其全厂电气主接线形式与大容量火力发电机组相比有其自身的特点,相应同期点的选择考虑角度也有所不同。本文结合实际的工程实例,介绍了垃圾焚烧发电厂选择同期点的设计思路,并提出了个人观点进行探讨。
The selection of synchronization point is closely related to the main electrical connection and operation mode.The power of the assembling units fluctuates from 9 to 30 MW,in the waste incineration power plant.For these small-load plants,which main electrical connection has its own characteristics,comparing with the large power plant,and the corresponding selection of synchronization point is also considered from different angles.Combined with practical engineering examples,this thesis introduce the design thought of selecting synchronization point,and presents the author’s own viewpoint.
出处
《有色设备》
2021年第3期43-46,63,共5页
Nonferrous Metallurgical Equipment
关键词
垃圾焚烧发电厂
同期点
waste incineration power plant
synchronization point