摘要
某年产30×10^(4)t/a煤制甲醇项目产生的废水包括气化废水、硫回收水、装置冲洗水等,废水处理设施设计规模为120 m3/h,采用调节池+沉淀池+SBR池+曝气生物滤池(BAF)+过滤+消毒为主的处理工艺。SBR池采用低负荷启动,控制进水结束时的氨氮<30 mg/L,出水氨氮<10 mg/L;再经BAF深度处理后,出水COD<50 mg/L,氨氮<5 mg/L,可回用于生产。
A coal-to-methanol project produces 30×10^(4) t/a of wastewater including gasification wastewater, sulfur recovery and rinse water. The design capacity of the wastewater treatment facilities is 120 m3/h, and the process includes regulating tank, sedimentation tank, SBR, BAF, filtration, and disinfection. The SBR pool was started at low load to control the influent NH3-N to be less than 30 mg/L at the end of the inflow phase, and the effluent NH3-N to be less than 10 mg/L. Then after the advanced treatment by BAF, the effluent COD is less than 50 mg/L, and NH3-N is less than 5 mg/L stably, which could be reused as production water.
作者
张刚
张颢琛
黄海鹏
吴智坤
ZHANG Gang;ZHANG Hao-chen;HUANG Hai-peng;WU Zhi-kun(Hangzhou Shengjing Environmental Protection Engineering Co.Ltd.,Hangzhou 310030,China)
出处
《中国给水排水》
CAS
CSCD
北大核心
2021年第10期142-146,共5页
China Water & Wastewater
关键词
煤制甲醇废水
废水回用
SBR工艺
曝气生物滤池
coal-to-methanol wastewater
wastewater reuse
SBR process
biological aerated filter