深厚淤泥质粉质黏土河道边坡抗滑措施研究 被引量:2

Study on anti-sliding measures of deep muddy silty clay river slope
下载PDF
导出
摘要 新孟河延伸拓浚工程南延段河道工程属于平地开河,为满足工程需求,河道设计采用放坡复式断面,沿线局部河段存在深厚淤泥质粉质黏土,该土层力学性能较差,河道边坡整体抗滑稳定安全系数难以满足规范要求。应用水泥土搅拌桩、预制钢筋混凝土方桩与地下连续墙等作为不同河道边坡抗滑措施,并从河道边坡整体抗滑稳定、边坡抗滑措施工程造价等方面进行多角度的对比分析,阐述工程采用地下连续墙进行河道边坡抗滑的优越性,为类似工程设计提供参考。 The south extension section of Xinmeng River Extension and Dredging Project belongs to the river opening on flat ground.In order to meet the engineering requirements,the river channel design adopted the slope-relief composite section.There were deep muddy silty clay in the local reaches along the line.The mechanical properties of the soil layer were poor,and the overall stability safety factor of the river slope was difficult to meet the specification requirements.Soil-cement mixing piles,precast reinforced concrete piles and underground continuous wall and so on were used as a different channel slope anti-sliding measures,and a multi-angle comparative analysis was carried out from the aspects of the overall anti-sliding stability of the river slope and construction cost of the anti-sliding measures of the slope.The advantages of using underground continuous wall for anti-sliding of river slope were expounded,which could provide reference for similar engineering design.
作者 郑宏伟 李昱 宋黎明 ZHENG Hongwei;LI Yu;SONG Liming(Jiangsu Taihu Planning and Design Institute of Water Resources Co.,Ltd.,Suzhou 215100,China)
出处 《江苏水利》 2021年第7期10-13,18,共5页 Jiangsu Water Resources
关键词 淤泥质粉质黏土 河道 边坡稳定 工程造价 地下连续墙 muddy silty clay river slope stability construction cost underground continuous wall
  • 相关文献

参考文献6

二级参考文献32

  • 1郭蓬捷,何秉顺,袁辉.改进的库水位骤降期边坡稳定分析方法[J].水利规划与设计,2006(5):29-33. 被引量:6
  • 2铁道部科学研究院西北分院.滑坡防治[M].北京:中国铁道出版社,1977..
  • 3《地基处理手册》编写委员会.地基处理手册,第2版[M].北京:中国建筑工业出版社,2000..
  • 4吴家惠.公路支档构造物[M].西安:西北工业大学出版社,1996..
  • 5王恭先.抗滑支挡建筑物的发展动向[A].铁道部西北研究院.滑坡文集(13)[C].北京:中国铁道出版社,1997.60-64.
  • 6王恭先.抗滑支挡建筑物的发展动向 [A].铁道部西北研究院.滑坡文集 (1 3 ) [C].北京 :中国铁道出版社,1997.60 -64.
  • 7陶小林,秦江伟.地震作用下边坡稳定预测方法的对比研究[J].水利规划与设计,2007(5):57-60. 被引量:5
  • 8Popescu M E. Liquid and slide causes to landslide remediation[M]. Rotterdam:AA Balkema,1996.
  • 9Schuster R L. Recent advances in slope stabilization[M]. Rotterdam: AA Balkema, 1996.
  • 10钱家欢,土工原理与计算,1996年

共引文献84

同被引文献15

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部