摘要
通过北京地铁某地铁车站的工程实践,研究了洞桩法(8导洞)工程从群洞开挖到扣拱期间的施工步序、工序转换和空间变形发展规律,综合分析了几何轴对称的车站结构断面在施工时差条件下导致的空间不均匀变形发展规律,对比工程数值模拟、实测数据,研究了工法执行差异是引起“地层结构”一体结构的空间不均匀空间变形的主要原因。经过对变形曲线的综合分析得知,形成的洞桩法结构周边的地层空间不均匀变形与空间临空、时空延续效应的叠加效果相关。最后针对性地制订工程对策并在工程中得以验证。本文的经验可以为类似工程的设计和施工提供有益的参考。
In this paper,through the study of the process transformation and settlement law of PBA method(8 pilot tunnel engineering)during the excavation of group tunnels to the arch buckle,the study comprehensively analyzes the spatial non-uniform deformation development law of the geometric axisymmetric station structure under the condition of construction time difference,and compares with the engineering numerical simulation and measured data.It is pointed out that the difference of construction method execution is the main reason for the uneven spatial deformation of“PBA tunnel and stratum”integrated structure.Through the comprehensive analysis of the deformation curve,it is found that the spatial uneven deformation of the surrounding strata is related to the superposition effect of spatial free space and space-time continuation effect.Finally,the project countermeasures are formulated and verified in the project.The experience of this paper can provide a useful reference for the design and construction of similar projects.
作者
付春青
刘波
Fu Chunqing;Liu Bo(General Contract Department of Rail Transit and Municipal Engineering,BeijingUni-Construction Group Co.,Ltd.,Beijing 100029,P.R.China;State Key Laboratory of Geomechanics and Deep Underground Engineering,Beijing 100083,P.R.China;School of Mechanics and Civil Engineering,China University of Mining&Technology,Beijing 100083,P.R.China)
出处
《地下空间与工程学报》
CSCD
北大核心
2021年第3期927-942,共16页
Chinese Journal of Underground Space and Engineering
基金
“十三五”国家重点研发计划(2016YFC080250504)。
关键词
洞桩法
非对称
地表沉降
空间演变
不均匀变形
PBA method
asy mmetry
surface settlement
spatial evolution
uneven deformation