摘要
水电工程赶工补偿费用的妥善处理,是工程顺利开展以及竣工验收的关键因素,针对水电工程的赶工补偿,分析了赶工补偿费用组成,对相关组成费用项目给出了计算方法,尤其对新增人工费以及施工降效费提出了赶工基数法和实物量法的计算方式。
Proper treatment of compensation fees for hurry work of hydropower project is a key factor for smooth development of the project and completion acceptance.Aiming at the hurry-work compensation for hydropower project,this paper analyses the components of hurry-work compensation fees,gives the calculation methods for related components,especially puts forward the calculation methods of hurry-work base number method and physical quantity method for newly added labor fees and construction cost reduction.
作者
于明远
YU Ming-yuan(Power China Kunming Engineering Corporation Limited,Kunming 650051,China)
出处
《云南水力发电》
2021年第7期260-262,共3页
Yunnan Water Power
关键词
赶工
费用组成
费用计算
水电工程
The crush.Cost
Cost calculation
Hydropower project