期刊文献+

大采高综采工作面过断层关键技术研究 被引量:7

Research on Key Technology of Large Mining Height Fully Mechanized Working Face Crossing Fault
下载PDF
导出
摘要 为保证大采高工作面安全高效过断层,以红阳三矿1210-2大采高综采工作面为工程背景,通过相似模拟试验及现场矿压监测的方式,提出了控制采高、沿断层下盘层位推进、伪斜开采、液压支架高工作阻力、追机移架等过断层措施。经现场实践,取得了良好的安全经济效益。 In order to ensure the safety and efficiency of large mining height working face passing through fault,taking the 1210-2 large mining height fully mechanized working face of Hongyang No.3 Mine as the engineering background,through similar simulation experiment and on-site mine pressure monitoring,the measures of controlling mining height,advancing along the footwall of fault,pseudo inclined mining,high working resistance of hydraulic support,and moving machine are put forward.Through field practice,good safety and economic benefits have been achieved.
作者 宋景利 谢廷深 刘兆辉 Song Jingli;Xie Tingshen;Liu Zhaohui(Hongyang No.3 Coal Mine of Shenyang Coking Coal Co.,Ltd.,Liaoning Liaoyang 111307)
出处 《山东煤炭科技》 2021年第7期50-52,共3页 Shandong Coal Science and Technology
关键词 大采高 综采 断层 large mining height fully mechanized mining fault
  • 相关文献

同被引文献44

引证文献7

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部