摘要
2208巷掘进时受上覆19#煤层采空区及煤柱影响,巷道围岩控制相对困难;为确保巷掘进安全,同时为8208综放工作面回采创造良好条件,拟采用工程类比法对在采空区下、煤柱下掘进的2208巷围岩控制方案进行专门设计;现场实践表明,顶底板、巷帮变形量分别只有31 mm、27 mm,围岩控制效果良好。
Aiming at the difficult surrounding rock control influenced by goaf of overlying No.19 coal seam and coal pillar in driving 2208 roadway,the author proposes the surrounding rock control scheme through engineering analogy method to designing at 8208 fully-mechanized working face,whose field practice shows that the surrounding rock is effectively controlled with deformation of 31 mm and 27 mm respectively in roof and floor and the roadway sides.
作者
马晋君
Ma Jinjun(Shuozhou Coal&Electricity Co.,Datong Coal Mine Group.,Huairen,Shanxi 038300)
出处
《江西煤炭科技》
2021年第3期16-18,共3页
Jiangxi Coal Science & Technology
关键词
近距离煤层
围岩控制
工程类比法
巷道掘进
close-distance coal seams
surrounding rock control
engineering analogy method
roadway excavation