IPD理念在大型主题公园项目中的实践研究 被引量:1

Practical Research on IPD Concept in Large Theme Park Project
下载PDF
导出
摘要 为研究集成项目交付(IPD模式)在我国的应用实践,结合国内外已有研究,从组织结构、合同体系、生命周期和技术支撑方面探讨IPD模式的主要特征,并指出其与传统交付模式的区别及在国内应用的限制。以北京某大型国际主题公园项目为例,探索论证在早期深度参与及各方共同决策、以正向BIM为技术支撑方面,利用IPD模式在国内建设项目中的实践,减少变更、大幅缩短工期效果,并提出相关思考。为确保IPD模式在我国的真正实施及实施质量,需增强各参与方的互相信任度与契约精神,积极从合约体系和技术层面营造该模式在我国实施的大环境。 To study the application practice of integrated project delivery(IPD mode)in China,the main characteristics of IPD mode,including organizational structure,contract system,life cycle and technical support,are investigated based on the existing researches at home and abroad.Besides,the differences between IPD mode and conventional delivery modes as well as the limitations of IPD application in China are also discussed.Then taking a large international theme park project in Beijing as an example,the practice of using IPD concept in domestic construction projects is explored and demonstrated from both deep participation and joint decision-making by all parties in early stages and using forward BIM as technical support.Such benefits as reduction of changes and great shortening of the construction duration have been achieved and some relevant considerations have been put forward.In order to ensure the real implementation and implementation quality of IPD model in China,it is necessary not only to enhance the mutual trust and contract spirit of all participants,but also to actively create a general environment for the implementation of the model in China from both the contract system and technical level.
作者 林佐江 王磊 周予启 王鸿章 常陆军 左一泽 宫圣岳 胡慧超 LIN Zuojiang;WANG Lei;ZHOU Yuqi;WANG Hongzhang;CHANG Lujun;ZUO Yize;GONG Shengyue;HU Huichao(China Construction First Group Construction and Developm nt Co.,Ltd.,Beijing100102,China;China State Construction Engineering Co.,Ltd.,Beijing100102,China)
出处 《施工技术》 CAS 2021年第12期20-24,共5页 Construction Technology
基金 中国建筑股份科技研发课题(CSCEC-2020-Z-31)。
关键词 交付模式 集成项目交付 建筑信息模型 理念 项目实践 delivery modes integrated project delivery(IPD) building information modeling(BIM) concept project practice
  • 相关文献

参考文献9

二级参考文献91

  • 1米旭明.工程项目合作关系的演化博弈分析[J].系统仿真技术,2007,3(4):225-228. 被引量:3
  • 2Lichting W.A., The Integrated A- greement for Lean Project Delivery [J], Contract Forms/Project Management, 2006, 26(3):25-32.
  • 3Zhang Y., Guangbin W.. Cooperation between Building Information Modeling and Integrated Project Delivery Method Leads to Paradigm ShiR of AEC Industry [J], Management and Service Science, 2009:1-4.
  • 4Kenig M., Allison M., Black B. et al. Integrated project delivery for public and private owners [EB/OL], www.agc. org/projectdelivery, 2010-09.
  • 5Novitski B.J.. New AIA agreement support integrated project delivery [EB/OL], http://archrecord.construction. com/practice/proj Delivery/0807aia.asp, 2008-07.
  • 6David A., Vashali A.. IPD: The AIADelivers a Multi-Party Agreement [EB/OL], http://www.zdlaw.corn/enews/2010/integrated-proj ect-delivery-ipd.php, 2010-02.
  • 7PatrickJ. O'Connol; Jr, Integratedproject delivery, collaboration through new contract forms[EB/OL], http://www.acecmn.rg/contents/file/194,2009-01 - 15.
  • 8Feniosky Pena-Mora, Michael Li. Dynamic planning and control methodology for design/build fast-track construction projects [ J ]. Journal of Construction Engineering and Management, 2001, 127 (1): 1-17.
  • 9George Elvin. Integrated practice in architecture: Mastering design-build, fast- track, and building information modeling [M]. New Jersey: John Wiley and Sons, 2007.
  • 10AIA Nation/AIA California Council. Integrated project delivery: a guide [M/OL]. Washington: The American Institute of Architects, 2007 [2010-10-30]. http: //www. betterbricks. com/ graphics/assets/documents/AIA-_ IPD_ Guide 2007. pdf.

共引文献101

同被引文献4

引证文献1

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部