桥梁现浇梁高位多向平移施工技术 被引量:4

High-position Multi-directional Translation Technology of Bridge Cast-in-place Beam
下载PDF
导出
摘要 为解决预制梁运输架设难题,结合成都地铁轨道交通10号线高架段施工实例,采用梁上运梁方式,使单线梁地板暂变双线,待运梁车与架桥机完成运梁、架梁工作后,采用同步顶升技术并安装组合式轨道进行横向推移,将梁体进行高位多向平移至设计原位。介绍了梁体横纵向位移控制关键技术,通过应用该技术,缩短施工工期、减小施工占用空间、降低施工成本。 In order to solve the problems of transportation and erection of prefabricated beams,combined with the elevated section of Chengdu Metro Rail Transit line No.10,this project adopts the beam-up beam method to temporarily change the single-line beam floor to double-line,and when the girder carrier and bridge erector finish the girder transport and erection work,synchronous jacking technology is adopted and a combined rail is installed for lateral pushing of the girder,and the girder body is shifted to the original design position by high position multi-directional translation.This paper proposes a key technology for horizontal and vertical displacement control of the girder,which shortens the construction period,reduces the construction occupation space,and saves the construction cost.
作者 毛长江 赵亚杰 古松 顾颖 MAO Changjiang;ZHAO Yajie;GU Song;GU Ying(China Railway Construction Group Co.,Ltd.,Beijing100040,China;School of Civil Engineering and Architecture,Southwest University of Science and Technology,Mianyang,Sichuan621010,China)
出处 《施工技术》 CAS 2021年第12期57-60,共4页 Construction Technology
关键词 桥梁工程 预制梁 单线梁 运梁车 顶升 多向平移 bridges prefabricated girder single girder girder carrier jacking multidirectional translation
  • 相关文献

参考文献4

二级参考文献10

共引文献27

同被引文献51

引证文献4

二级引证文献16

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部