摘要
The paper proposes a stochastic unit commitment(UC)model to realize the low-carbon operation requirement and cope with wind power prediction errors for power systems with intensive wind power and carbon capture power plant(CCPP).A linear re-dispatch strategy is introduced to compensate the wind power deviation from the spot forecast.The robust optimization technique is employed to obtain a reliable commitment plan against all realizations of wind power within the uncertainty set given by probabilistic forecast.The proposed model is validated with IEEE 39-bus system.The advantages of flexible CCPPs are compared to the normal coal-fueled plants and the impacts of robustness controlling are discussed.
基金
This work was supported by the National Basic Research Program of China(No.2012CB215106)
State Grid Corporation of China(No.52150014006W).