目前LNG储罐已实现全面自主设计、自主建造,且随着单罐设计容积的逐渐增大,对设计和建造提出更高的技术要求。结合目前已建LNG储罐在桩基础设计、施工阶段发生的常见问题进行总结、分析,为后续大型化储罐桩基础设计施工提供可选择性的解决方案。
At present,LNG storage tanks have been fully designed and built independently.With gradual increase of single tank design volume,higher technical requirements are put forward for design and construction.The common problems are summarized and analyzed,so as to provide alternative solutions in design and construction for the subsequent large-scale LNG storage tank pile foundation.