基于Matlab的转桨式恒速风电机组三相短路故障分析 被引量:1

Analysis of Three-phase Short-circuit Fault in Wind Turbine With Fixed Speed and Rotatable Paddle Based on Matlab
下载PDF
导出
摘要 针对定速转桨风电机组,基于Matlab建立发电机的数学模型,阐述对于并网运行过程中发生的三相短路故障仿真和分析,在基本风及渐风输入模式下产生的特征参数变化及对系统稳定性的影响。 This paper takes the fixed-speed wind generator as the research object. It establishes a mathematical model of the generator based on Matlab and simulates and analyzes the three-phase short-circuit fault occurring in the process of grid-connected operation so as to further explore the change of characteristic parameters and its influence on system stability under basic wind and gradual wind input mode.
作者 张超超 裴建康 黄潇彬 潘梅 李隆 Zhang Chaochao;PEI Jiankang;HUANG Xiaobin;PAN Mei;LI Long(State Grid Akesu Electric Power Supply Company,Akesu 843000,China;Hubei Electric Power Co.,Ltd.,Zaoyang Power Supply Company,Xiangyang 443001,China)
出处 《集成电路应用》 2021年第7期104-105,共2页 Application of IC
关键词 定速风力发电机 三相短路故障 无功补偿 低电压穿越 constant speed wind generator three phase short circuit fault reactive power compensation low voltage crossing
  • 相关文献

参考文献1

二级参考文献20

  • 1World Wind Energy Association (WWEA). World WindEnergy Report 2010[R]. 2011.
  • 2中国国家标准化管理委员会.GB/T19963-2011风电场接入电力系统技术规定[S].北京:中国标准出版社,2012.
  • 3Federal Energy Regulatory Commission (FERC, USA).Interconnection for wind energy 18 CFR part[EB/OL].3 5 [2005-06-02] ? http://www.ferc.gov.
  • 4E.ON Netz (Germany). Grid code high and extra highvoltage. E.ON Netz GmbH, Bayreuth[EB/OL]. [2006].http://www.pvupscale.org.
  • 5FINGRID OYJ. Connection code for connection of windpower plants to finish power system,Nordel connectioncode for wind turbines and country-specific additionalspecification for connection of wind turbines to finishpower system[EB/OL]. [2009-03]. http://www.fingrid.fi.
  • 6National Grid Electricity Transmission PLC(UK). Thegrid code issue 4, revision 13[EB/OL]. [2012-06-07].http://www.nationalgrid.com.
  • 7Technical Regulation TF 3.2.5 (Denmark). Wind turbinesconnected to grids with voltages above 100 kV. Elkraftsystem and eltra[EB/OL]. [2004-12-03].http://www.energinet.dk.
  • 8Regulations for Grid Connection TF 3.2.3 (Denmark).Technical regulation for thermal power station units of1.5 MW and higher, Version 5.1[EB/OL]. [2008-10].http://www.energinet.dk.
  • 9Australian Energy Market Commission. Nationalelectricity rules -chapter 5 - grid connection, version51 [EB/OL]. [2012-08-02]. http://www.aemc.gov.au.
  • 10EIRGRID (Ireland). EirGrid grid code, version4.0[EB/OL]. [2012-12-08]. http://www.eirgrid.com.

共引文献18

同被引文献11

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部