期刊文献+

考虑瓶颈工序外协的模具车间调度研究与应用 被引量:1

Research and Application of Die&Mold Shop Scheduling for the Considering Bottleneck Process Outsourcing
下载PDF
导出
摘要 瓶颈工序是工件生产流动的窄口,直接影响产品的交货期和制造成本。模具生产为典型的多品种小批量生产方式,生产节拍难以控制,生产调度困难,瓶颈工序直接制约车间产量的提升。以最大化利润为调度目标,研究考虑瓶颈工序外协的调度算法,并在某公司模具车间进行运用,取得了较好的效益,验证了该调度算法对多目标柔性作业车间的指导意义。 The bottleneck process is the narrow gap of production flow,which directly affects the delivery time and manufacturing cost of products.Die&mold production is a typical multi variety and small batch production mode.It is difficult to control the production rhythm and scheduling.Bottleneck process directly restricts the improvement of workshop output.In order to maximize profit as the scheduling objective.This paper studies the scheduling algorithm considering bottleneck process outsoureing,and applies it in a mold workshop of a company,and achieves good benefits,which verifies the guiding significance of the scheduling algorithm for multi-objective flexible job shop.
作者 顾伟栋 宋利刚 李占鑫 Gu Weidong;Song Ligang;Li Zhanxin(Citic Dicastal Co.,Ltd.,Qinhuangdao,Hebei 066004,CHN)
出处 《模具制造》 2021年第8期5-9,共5页 Die & Mould Manufacture
关键词 瓶颈工序 多品种小批量 生产调度 模具 botleneck process multi-variety and small-batch production scheduling die&mold
  • 相关文献

参考文献5

二级参考文献57

  • 1夏蔚军,吴智铭.基于混合微粒群优化的多目标柔性Job-shop调度[J].控制与决策,2005,20(2):137-141. 被引量:35
  • 2蔡良伟,李霞,张基宏.用带蚁群搜索的多种群遗传算法求解作业车间调度问题[J].信息与控制,2005,34(5):553-556. 被引量:11
  • 3谷峰,陈华平,卢冰原,古春生.粒子群算法在柔性工作车间调度中的应用[J].系统工程,2005,23(9):20-23. 被引量:15
  • 4Bruker P, Schlie R. Job- shop Scheduling with Multi-- purpose Machines[J]. Computing, 1990,45 (4) :369-375.
  • 5Brandimarte P. Routing and Scheduling in a Flexible Job Shop by Tabu Search[J]. Annals of Operations Research,1993,41(3) :157-183.
  • 6Mati Y, Rezg N, Xie X L. An Integrated Greedy Heuristic for a Flexible Job Shop Scheduling Problem[C]//2001 IEEE International Conference on Systems, Man, and Cybernetics. Tucson, AZ: IEEE, 2001 : 2534-2539.
  • 7Hapke M. Pareto Simulated Annealing for Fuzzy Multi -- objective Combinatorial Optimization[J]. Journal of Heuristics,2000,6(3) :329-345.
  • 8Rigao C. Tardiness Minimization in a Flexible Job Shop: a Tabu Search Approach[J]. Journal of Intelligent Manufacturing, 2004,15 (1) : 103-115.
  • 9Dauzere- Peres S,Paulli J. An Integrated Approach for Modeling and Solving the General Multiprocessot Job- shop Scheduling Problem Using Tabu Search[J]. Annals of Operations Research, 1997, 70:281-306.
  • 10Mastrolilli M, Gambardella L M. Effective Neighborhood Functions for the Flexible Job Shop Problem[J]. Journal of Scheduling, 2002,3 (1) : 3-20.

共引文献94

同被引文献7

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部