摘要 北京地铁17号线盾构接收井横通道开挖施工中,发现下层导洞含水量大,虽采用全断面注浆残余水仍难以控制。对此将小型潜水泵接入轻型井点作为暗挖隧道止水措施,经计算根据隧道的最大涌水量确定了轻型井的各项参数;采用倾斜成孔等施工工艺,取得了良好的止水效果。 During excavation of cross passage of shield receiving shaft of Beijing Metro Line 17, it was found that the lower pilot tunnel has a large water content, and the residual water is still difficult to control despite the use of full-section grouting. For the above, a small submersible pump is connected to a light well point as a water-stop measure for the underground excavation tunnel. After calculation, various parameters of the light well are determined according to maximum water inflow of the tunnel;and construction techniques such as inclined hole formation have been used to achieve good water-stopping effect.
作者 周天豪 吴昊 ZHOU Tian-hao;WU Hao(Beijing Construction Engineering Group Co.,Ltd.,100055,Beijing,China)
出处 《建筑技术》 2021年第8期973-975,共3页 Architecture Technology
关键词 轻型井点 隧道工程 止水效果 light well point tunnel engineering water stop effect
  • 相关文献

参考文献4

二级参考文献11

共引文献13

同被引文献12

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部