摘要 随着大力发展地铁建设,明挖车站基坑工程越来越多,而基坑坍塌、失稳事件频频发生,其中有一半以上是直接或者间接与基坑土体内的水相关,降雨是导致基坑发生变形、失稳、破坏的主要诱导因素之一。以成都地铁19号线二期工程合江站及站前站后明挖区间基坑工程防洪度汛为背景,从汛期暴雨强度、基坑周边及基坑汇水、沟渠行洪能力验算、水泵配置和选型等角度进行分析计算,制定针对性应对措施,为雨季施工安全度汛提供了有力的技术支撑。 With the vigorous development of subway construction,more and more open-cut station foundation pit works have been built.Foundation pit collapse and destabilization occur frequently,more than half of which are directly or indirectly related to water in the soil body of the foundation pit.Rainfall is one of the main inducing factors leading to deformation,destabilization and destruction of the foundation pit.Taking the second phase project of Chengdu Metro Line 19 as background,this paper makes analysis and calculation from the perspectives of rainstorm intensity in flood season,collection of water around foundation pit and foundation pit,checking calculation of flood carrying capacity of ditches,allocation and selection of pumps.This paper formulates corresponding measures,which provide strong technical support for construction safety during rainy season.
作者 沈陈 管元勇 撒雪艳 高小红 徐强 SHEN Chen;GUAN Yuan-yong;SA Xue-yan;GAO Xiao-hong;XU Qiang(POWERCHINA SINOHYDRO ENGINEERING BUREAU 14 CO.,LTD.,Kunming 650041,China)
出处 《云南水力发电》 2021年第8期17-23,共7页 Yunnan Water Power
关键词 地铁 明挖车站基坑工程 防汛 验算 metro open-cut station foundation pit engineering flood control checking
  • 相关文献

参考文献1

二级参考文献5

  • 1GB50497-2009,建筑基坑工程监测技术规范[S].
  • 2JTGE40-2007,公路土工试验规程[S].
  • 3JGJ120-2012,建筑基坑支护技术规程[S].
  • 4GB50112-2013,膨胀土地区建筑技术规范[S].
  • 5汪波,聂前勇,王运生,张建永.也论成都粘土的成因[J].地质灾害与环境保护,2002,13(1):54-56. 被引量:30