地铁工程400V受电探究

Research on 400V Power Acceptance of Subway Project
下载PDF
导出
摘要 400V受电是地铁站后工程施工过程中一个关键的时间节点,是开展地铁工程机电设备调试和试运行的前提条件,且受电实施过程安全风险较大,安全、按时完成400V受电对保证地铁工程的施工进度具有重要影响。结合1个地铁工程400V受电的案例,从受电计划安排、工作准备、组织实施、安全管控措施等几个方面对地铁工程400V受电工作展开论述,系统、完整地阐明了地铁工程400V受电的实施过程和安全管控重点。 400V power acceptance is a key time node in the construction process of the post-subway project and a prerequisite for commissioning and commissioning of electromechanical equipment in the subway project.Safety risk is high during the implementation of power acceptance.Safe and timely completion of 400V power acceptance has an important influence on the construction progress of subway projects.Based on a case study of 400V power acceptance of subway project,this paper discusses 400V power acceptance of a subway project from several aspects such as power supply plan arrangement,work preparation,organization and implementation,safety management and control measures,and systematically and completely clarifies the implementation process and key points of safety management and control of 400V power acceptanceof subway project.
作者 李开存 LI Kai-cun(POWERCHINA SINOHYDRO ENGINEERING BUREAU 14 CO.,LTD.,Kunming 650041,China)
出处 《云南水力发电》 2021年第8期164-167,共4页 Yunnan Water Power
关键词 地铁工程 400V受电 低压开关柜 安全管控 subway project 400V power acceptance low voltage switch cabinet safety control
  • 相关文献

参考文献6

二级参考文献12

共引文献10

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部