摘要 根据坡月水库工程的地质条件,对9个重力坝岸坡坝段在考虑不同剪切面情况下的侧向抗滑稳定系数进行计算分析。结果表明:在本工程中采用不同剪切面假定方法计算得到的抗滑稳定安全系数均能满足规范要求,但计算结果存在偏差。根据实际地质参数采用合适剪切面假定及计算方法,对重力坝岸坡坝段的侧向抗滑稳定计算是十分重要的。 According to the geological conditions of Poyue Reservoir,the lateral anti-sliding stability coefficients of nine gravity dam blocks under different shear planes were calculated and analyzed.The results demonstrate the an⁃ti-sliding stability safety factors calculated by different shear plane assumption methods all meet the requirements of code,but there exit deviation between the calculation results.It is very important to calculate the lateral anti-slid⁃ing stability of the bank-side dam blocks of gravity dam by proper shear plane assumption and calculation method according to the actual geological parameters.
作者 刘惠娟 LIU Hui-juan(Guangxi Vocational College of Water Resources and Electric Power,Nanning 530023,China)
出处 《广西水利水电》 2021年第4期71-74,共4页 Guangxi Water Resources & Hydropower Engineering
关键词 重力坝 抗滑稳定 剪切面假定 计算分析 坡月水库 Gravity dam anti-sliding stability shear plane assumptions calculation and analysis Poyue Reservoir
  • 相关文献

参考文献2

二级参考文献2

共引文献7

同被引文献4

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部