摘要
文章围绕洛阳电网3座220 kV变电站(半)高型高压配电装置改造设计方案,通过时间跨度15年的5个220 kV、110 kV(半)高型高压配电装置改造工程设计实例,总结了(半)高型高压配电装置的改造经验。
The article focuses on the design plan for the transformation of 3220 kV substations(semi)high-voltage power distribution devices in Luoyang Power Grid,and passed the design examples of 5220 kV,110 kV(semi)high-voltage power distribution equipment renovation projects with a time span of 15 years,summarizes the retrofit experience of(semi)high-voltage power distribution equipment.
作者
王喜俊
邵薇
Wang Xi-jun;Shao Wei
出处
《电力系统装备》
2021年第12期87-88,共2页
Electric Power System Equipment
关键词
洛阳电网
220
kV变电站
(半)高型高压配电装置改造
设计
研究
Luoyang Grid
220 kV substation
the transformation of(semi)high-type high-voltage distribution devices
design
research