摘要
以粤东山区大潮高速公路浅埋偏压隧道梅岭隧道为背景,开展围岩预加固措施及进洞施工优化研究,并根据实际应用评价优化效果。研究结果表明,在隧址区降雨量充沛和工期紧的特殊条件下,采用“管棚+地表小导管注浆+混凝土反压护拱”的措施能较好地起到围岩超前加固的作用,该加固条件配合“短台阶预留核心土法”进洞施工,施工安全和工期得到了较好的保障。依托工程采用优化方案后,进洞施工总体较为顺利,仅在洞内初期支护上出现轻微裂缝,开展裂缝监测和结构验算后进一步表明,该初支裂缝为浅层的,二次衬砌施工后可确保结构安全。
In this paper,taking the shallow-buried and unsymmetrical-loaded Meiling Tunnel of Dachao Expressway in eastern mountainous area of Guangdong Province as an example,research on optimization of pre-reinforcement measures on rock masses and excavation plan has been carried out,the optimization results have been evaluated.It has shown that,in rainy and tight-scheduled condition,"pipe roof+surface grouting+concrete arch"in accompany with"step excavation with core soil"could strengthen the surrounding rocks,ensure construction safety and conform to the time limit of a project.Structure checking suggests that the minor crack on shoot concrete will be eliminated once the second lining is applied.
作者
官治立
GUAN Zhili(Guangdong Communications Industrial Investment Co., Ltd., Guangzhou 510623)
出处
《广东公路交通》
2021年第4期164-169,共6页
Guangdong Highway Communications
基金
广东省交通运输厅科技项目(编号:科技-2017-02-005)。
关键词
浅埋偏压隧道
施工优化
进洞方案
shallow-buried unsymmetrical-loaded tunnel
construction optimization
plan of tunnel excavation