摘要
结合法规标准要求,国内外核电厂主控室大屏幕应用情况以及实际工程经验,对核电厂应急指挥中心大屏幕选型、系统配置、布置设计、抗震设计、画面设计等关键环节进行深入分析探讨,并总结出工程设计应用中的技术要点,为后续指挥大厅大屏幕设计及应用提供参考和借鉴。
Combined with the requirements of regulations and standards,the application of large screen in main control room of nuclear power plant at home and abroad and the practical engineering experience,the key links of large screen selection,system configuration,layout design,seismic design and screen design of emergency command center of nuclear power plant are analyzed and discussed in depth.The technical points of engineering design and application are summarized,which will provide the design and application of large screen for the follow-up command hall.Provide reference and reference.
作者
陈政涛
李磊
张龙强
王晓宇
刘洪涛
Chen Zhengtao;Li Lei;Zhang Longqiang;Wang Xiaoyu;Liu Hongtao(China Nuclear Power Design Co.,Ltd.,Guangdong,Shenzhen,518000,China)
出处
《仪器仪表用户》
2021年第9期60-63,共4页
Instrumentation
关键词
核电厂
应急指挥中心
大屏幕显示
nuclear power plant
emergency command center
large screen display