摘要
介绍了尿素装置配套CO_(2)离心压缩机组的工艺流程以及原始试车和运行期间出现的问题。重点就投料试车过程中出现的高压缸轴端漏气量大、高压缸主止推瓦温度高、运行期间出现的二段出口冷却器列管泄漏、高压缸主止推瓦瓦温持续缓慢上涨等问题及其采取的解决措施进行了阐述。通过技改或检修等措施,消除了影响CO_(2)机组满负荷平稳安全运行的因素,保障了尿素装置的长周期稳定运行。
The process flow of C0_(2) centrifugal compressor unit in urea plant and the problems occurred during the original commissioning and operation are introduced.The paper focuses on the problems of gas large leakage of high pressure cylinder shaft end,high temperature of high pressure cylinder main thrust shoe,tube leakage of secondary outlet cooler during operation,continuous slow rise of temperature of high pressure cylinder main thrust shoe during the trail run and the measures taken to solve them.Through measures such as technical retrofit or maintenance,the factors affecting the stable,safe and full load operation of C0_(2) centrifugal compressor unit have been eliminated,and the long-term stable operation of the urea plant has been guaranteed.
作者
万树文
王洪振
董芳玺
WAN Shuwen;WANG Hongzhen;DONG Fangxi(Shandong Hualu-hengsheng Chemical Co.,Ltd.,Dezhou 253024,Shandong Province)
出处
《氮肥技术》
CAS
2021年第4期44-46,共3页
Nitrogenous Fertilizer Technology
关键词
CO_(2)离心机组
问题
措施
效果
C0_(2)centrifugal compressor unit
problem
measure
effect