期刊文献+

全级配预冷混凝土生产方法研究

Production method of full-graded precooled concrete
下载PDF
导出
摘要 为解决全级配预冷混凝土生产中预冷砂的问题,定量分析了砂温与混凝土出机口温度、片冰用量的关系,以及生产7℃,9℃,11℃全级配预冷混凝土的砂温适用范围;提出了用冷水与砂混合,再经二次机械振动脱水的冷砂方法,并进行了关键工艺试验。结果表明:该方法可有效降低砂温且保证砂含水率稳定,实现全级配预冷混凝土生产。 To solve the problem of sand precooling in the production of full-graded precooling concrete,we quanti⁃tatively analyzed the relationship between sand temperature and concrete temperature out of mixers,flake ice amount,as well as the suitable sand temperature range for the production of 7℃,9℃,11℃full-graded precooling concrete.We proposed a cooling sand method that mixing the sand with cold water then secondary dehydrating by mechanical vibration,and carried out the key technological tests.The results showed that the method can reduce the sand temperature and ensure stable moisture content,so realize production of full-graded precooling concrete.
作者 雷畅 刘盟盟 李倩 严君汉 卞小草 LEI Chang;LIU Mengmeng;LI Qian;YAN Junhan;BIAN Xiaocao(Changjiang Survey,Planning,Design and Research Co.,Ltd.,Wuhan 430010,China)
出处 《水利水电快报》 2021年第9期60-63,69,共5页 Express Water Resources & Hydropower Information
关键词 全级配预冷混凝土 水冷砂 砂温 混凝土温度 full-graded precooling concrete mixing the sand with cold water sand temperature concrete tempera⁃ture
  • 相关文献

参考文献4

二级参考文献3

共引文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部