摘要
针对220 kV输电线路融冰前需检修人员高空搭接融冰电缆头的弊端,提出并研制了一种220 kV融冰接地隔离开关。融冰实践证明该设备操作简便,可快速打通融冰通道,完全消除了检修人员高空作业的安全风险,满足大电流融冰要求。
Aiming at the disadvantages that maintenance personnel need to lap the ice-melting cable head at high altitude before ice-melting of 220 kV transmission lines, a new type of disconnector with both ice-melting and grounding functions is proposed and developed in this paper. Through the practical test of ice-melting, it is proved that the equipment is easy to operate, which can quickly open the ice melting channel, completely eliminates the safety risk for maintenance personnel working high above the ground, meets the requirements of high current ice melting.
作者
段明才
谭倩
乐耀璟
李志为
段华文
廖胜晖
DUAN Mingcai;TAN Qian;LE Yaojing;LI Zhiwei;DUAN Huawen;LIAO Shenghui(State Grid Chenzhou Power Supply Company,Chenzhou 423000,China)
出处
《湖南电力》
2021年第4期48-51,共4页
Hunan Electric Power
基金
国家湖南省电力有限公司群众创新项目(5216A0200033)。
关键词
融冰
接地
新型
安全风险
大电流
ice melting
grounding
new type
safety risk
high current