下凯富峡水电站碾压混凝土大坝层、缝间处理工艺 被引量:3

Treatment Technology for Layers and Joints of RCC Dam of Kafue Gorge Lower Hydropower Station
下载PDF
导出
摘要 传统的碾压混凝土坝施工过程中,停盘冲毛后的水平施工缝面浇筑混凝土前,或者超过碾压混凝土直接铺筑时间的层面,一般均采用铺设水泥砂浆的方法进行层、缝面结合处理。赞比亚下凯富峡水电站碾压混凝土层面处理引入成熟度概念,在层缝面根据修正成熟度值采用铺洒水泥净浆替代水泥砂浆,检查结果,效果良好,且方便快捷。 In traditional construction process of RCC dams,the horizontal construction joints after scouring and before pouring concrete,or the layers that exceed the direct paving time of RCC,generally adopt the method of laying cement mortar to deal with the bonding between layers and joints.The RCC layer treatment of the Kaifu Gorge Lower Hydropower Station in Zambia introduced the concept of concrete maturity.According to the revised maturity value,the cement paste was used to replace the cement mortar on the seam surface.The inspection indicates favorable effect and the construction process is convenient and efficient.
作者 高元博 靳俊杰 GAO Yuanbo;JIN Junjie(PowerChina Sinohydro Bureau 11 Co., Ltd., Zhengzhou 450001,China)
出处 《西北水电》 2021年第4期52-55,共4页 Northwest Hydropower
关键词 碾压混凝土 层间结合 水泥净浆 集中制浆站 Roller Compacted Concrete interlayer bonding cement paste centralized pulping station
  • 相关文献

参考文献4

二级参考文献3

共引文献10

同被引文献35

引证文献3

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部